Asset Publisher
Network Access Mode
Connection to the electricity transmission grid and clearing the site | Any applicant complying with the legal provisions is granted access to the transmission grid, while observing the norms and performance provided in the applicable technical regulations (the Technical Code of the Transmission Grid and related technical norms/regulations; conditions of the transmission licence) |
Legal grounds |
|
Stages |
|
Types of contracts |
|
Special account | A special account opened for the amounts charged from the connection tariffs |
Transelectrica Approval | Transelectrica's consultation and approval are needed also for connections to the electricity distribution grid. This requires cooperation between Transelectrica and the distribution operators. Solutions by means of study/research topics are required in order to perform the connection, such as- study to determine the power steps characterising the connection of a user to a certain voltage level under the configuration of Romania's Power System; solutions to connect certain consumers to the 220-400 kV OHL, correlation being required also with other projects (investments, maintenance, EMS/SCADA). |
Stages of the connection process |
|
Stages of issuing the location approval |
|
Regulations on grid access |
|
- Handbook for the users requesting connection of new generation or consumption places to the electricity transmission grid
- Handbook for the users requesting the sitting permit from CNTEE Transelectrica SA
- Applicants' guide for the wind power plants (WPPs) connection to the power transmission grid
-Wind forecasting example file